GRACE CHRISTIAN ACADEMY

“Using Design-Build shaved six months off our construction schedule. Construction Plus overcame several hurdles and delivered terrific results for us and our students.”

– Don Criss, Grace Christian Academy

*Click images to enlarge

[nggallery id=8]

CPI worked as a part of the team from day one to meet the project budget. At the end of Design-Development, based on the school’s needs, the estimated cost was $500K over the Board’s budget. Through innovative bid strategies and scope definitions the final bids were opened and ALL the school’s needs met, for 5% less than the Design-Development budget, which was also well below the original target budget.

  • Client: Grace Baptist Church
  • Project: Design-build project developing entire campus for the Academy and building the first phase, which is a high school.
  • Total Cost: $7,000,000
  • Scheduled Completion: Completed: Fall 2006

For more information on this project, please contact us.