MOSHEIM MIDDLE SCHOOL

“Construction Plus has done a great job of finding a way to build the facilities we need at the price we can afford. They delivered for the students of Greene County.”

– Ms. Lena Ensor, 2003 Chairman Greene Co. School Board

*Click images to enlarge

[nggallery id=10]

The new middle school will serve up to 375 students initially, with future expansion possible to handle up to 425 students. The addition will include 13 large classrooms, a gymnasium, a science lab, a computer lab, a library/media center, an in-school suspension room, a cafeteria and a band room.

Although the needs identified during design development were estimated to cost $200K more than the Board’s budget, innovative bidding techniques and scope packaging resulted in actual bids 5% less than the Design Development budget, allowing the Board to meet ALL their needs for less than the original budget

  • Client: Greene County Board of Education
  • Opened: December 2003
  • Total Cost: $4,404,057
  • Value: Final Cost 5% Under Budget
  • Change Orders: Less than 1%
  • Schedules: Completed ahead of schedule

For more information on this project, please contact us.